Carpenter Bee guide cover: kitchen renovation cost in Ontario

Quick answer

In short

A mid-range kitchen renovation in Ontario runs roughly $30,000 to $55,000 in 2026, and $40,000 to $75,000 in Toronto and the GTA, where published guides put prices 25–40% above the national average. A cosmetic refresh starts around $15,000. Above $65,000 you are in custom cabinetry and stone.

The line that moves your number most is not the countertop. It is whether the sink, the stove and the walls stay where they are. Moving plumbing adds $2,500 to $5,500 on its own, before anyone has picked a tile.

Published price ranges for 2026

SourceScopeRange
RenoQuotes, Canada kitchen cost guide, updated 4 September 2026Basic / mid-range / high-end$15,000–$25,000 / $30,000–$55,000 / $65,000+
RenoQuotes, same guideToronto and GTA mid-range$40,000–$75,000
Kitchen & Bath Renovation, Toronto cost guide, updated 8 April 2026Budget / mid-range / high-end$15,000–$20,000 / $20,000–$45,000 / $45,000–$70,000+

These are guides published by renovation companies and quote-matching sites, not government statistics. Statistics Canada tracks renovation spending in aggregate; nobody publishes an official price for a kitchen. Two sources that broadly agree are worth more than one that sounds confident, which is why both are here — and you can see they do not agree exactly.

Where the money actually goes

ItemShare of budgetTypical cost
Cabinetryabout 30%$250–$400 per linear foot in melamine, $850+ in solid wood
Appliancesabout 15%$3,000–$6,000 for a basic package
Labour and installation16–25%Cabinet installation $80–$120 per hour; a medium kitchen install $5,000–$12,000
Countertopsabout 10%$35–$70 per sq ft laminate, $110–$180 per sq ft quartz
Flooringabout 8%$1,500–$6,000
Plumbing—$1,500–$4,500 on existing rough-in; add $2,500–$5,500 to relocate
Electrical—$80–$150 per hour, and it must be done by a licensed electrical contractor
Lightingabout 4%$800–$3,000, or $100–$400 per fixture
Backsplash—$800–$2,500

Why are two quotes for the same kitchen $25,000 apart?

Almost always one of four things, and none of them is greed.

  1. Cabinet grade. Melamine boxes with laminate doors against solid wood with dovetail drawers is a three-fold difference on 30% of the budget. Ask what the boxes are made of, not what the doors look like.
  2. Layout changes. One quote assumes the sink stays under the window. The other prices moving it across the room. That single decision carries plumbing, drywall, flooring patching and often electrical with it.
  3. What is excluded. Appliances, lighting fixtures, backsplash and disposal are the four items most often left out of the cheaper quote.
  4. Who does the electrical. A licensed electrical contractor filing an ESA notification costs more than a general labourer with a drill. Only one of those two leaves you insurable.

Do I need a building permit for a kitchen renovation?

For a straight swap — same layout, new cabinets, new counters, same plumbing and electrical locations — usually no. You are into permit territory once you remove or move a wall, relocate plumbing, add circuits, or change a window or exterior door.

Electrical work is separate from the building permit. In Ontario it has to be done by a licensed electrical contractor who files a notification with the Electrical Safety Authority, and that applies even to small jobs like adding an island outlet. Our permit guide covers what needs one and who applies.

How long does a kitchen renovation take?

Four to eight weeks of site work for a typical mid-range kitchen is a realistic expectation, once demolition starts. The part people underestimate is what happens before that: custom cabinets are commonly quoted at six to ten weeks lead time, and stone is templated only after the cabinets are installed.

Ask for the schedule to name the cabinet order date. A contractor who can tell you when the cabinets were ordered is running a project. One who cannot is hoping.

Red flags in a kitchen quote

What you seeWhy it mattersWhat to do
“Cabinets included” with no brand, line or box materialCabinets are a third of your budget and the range is enormousAsk for the manufacturer, the door line and the box construction in writing
Countertop given as a lump sumStone is priced per square foot and by edge profile and cutoutsAsk for the material, the thickness, the square footage and what the sink cutout costs
No line for appliances or disposalThese reappear later as “not included”Confirm in writing who buys and installs appliances and who removes the old kitchen
Electrical priced without a licensed contractor namedUnfiled electrical work is a problem at resale and with insuranceAsk for the ECRA/ESA licence number of the company doing the wiring
Deposit above 10%Ontario’s own guidance to homeowners is no more than 10% downTie the larger payment to cabinet delivery, not to a date
A start date but no cabinet order dateThe cabinets are the long pole; everything waits on themPut the order date and the lead time in the contract

What to do next

Before you call anyone, decide one thing: does the sink move? Write the answer at the top of the page you hand to every contractor, and you will get three quotes you can actually compare instead of three different projects.

Then get the quotes in writing with the items above broken out. Your rights on a renovation contract covers the 10-day cancellation window and the 10% limit on going over an estimate, and how to check an Ontario contractor covers WSIB, insurance and the ECRA/ESA licence you should be asking for anyway.

When you are ready, browse renovation companies or choose your city and contact two or three directly. Carpenter Bee is a classified directory. We do not vet the companies listed here and a listing is not a recommendation — the checks are yours to make.

Frequently asked questions

Cost guides commonly quote partial recovery at resale rather than full return, and the figure varies by market and by how the kitchen suits the rest of the house. Treat any specific percentage you read as an estimate, not a promise.

Relocating plumbing usually requires a permit, and the plumbing must be done by a licensed plumber. Confirm with your municipality’s building department before the work starts, and put in the contract who applies for the permit.

Ontario’s guidance to homeowners is no more than 10% down. For custom cabinets, tie the next payment to their delivery rather than to a calendar date, so your money moves when materials do.

Refacing keeps the boxes and replaces doors and fronts, so it costs less than new cabinetry and takes less time. It only works when the existing boxes are sound and the layout already suits you.

Cabinetry, at around 30% of the budget, followed by appliances at about 15% and labour at 16–25%. Countertops, which people worry about most, are typically around 10%.

Published 2026 guides put a cosmetic refresh of a small kitchen at roughly $15,000 to $25,000 — new doors or stock cabinets, counters, backsplash and paint, with the layout and plumbing left alone. Moving anything pushes it past that band quickly.

Sources

  • RenoQuotes, Kitchen renovation cost in Canada in 2026, updated 4 September 2026 — renoquotes.com
  • Kitchen & Bath Renovation, Kitchen renovation cost Toronto 2026, updated 8 April 2026 — kitchenandbath.ca
  • Government of Ontario, Your rights when starting home renovations or repairs — ontario.ca, checked 18 September 2026

Prices are published ranges collected on 18 September 2026, not quotes. Costs move with material choice, kitchen size and what is found behind the walls. Get local quotes before you budget.